article

Sakeni Construction

The first large-scale project of the development company, "Biograpi Living," is the multi-functional residential complex Sakeni, and its construction is underway. This article will detail the construction progress.

Completed Works

It has been several months since the construction of Sakeni entered the active phase. By this time, the foundation of the complex area has been finished, beginning with the arrangement of the beams and preparatory works for the foundation, concrete slab laying, and preparation of high-quality tools and works.

An underground floor has also been arranged in the residential complex area adjacent to the pool. The parking tile has been covered on two sections of the first floor. 

|  |

Current Works

At this stage, the following construction works are in progress for Sakeni:

  • Roofing works of the underground floor of the main building, 50% completed
  • Arrangement of the first above-ground columns and apertures
  • Arrangement of parking on the 1st-floor slab
  • Installation of a powerful turret crane on the first crane with high load capacity
  • Heat insulation of commercial areas
  • Backfilling of the land to increase usable space<

|  |

The work is carried out under the constant supervision of the contractor's construction company.The construction of the multifunctional residential project is carried out by the "Anagi" company. The construction company has 35 years of experience and more than 170 local and foreign clients, showcasing their professionalism and reliability.

For Sakeni's production system, Biograpi Living cooperates with the Swiss company Sika. SikaProof is a renowned system recognized for its high quality. The TPO membrane system is characterized by the highest water retention capacity. SikaProof was used in the building's foundation, which, along with its water resistance, ensures the residential complex is 100% safe.

The construction of Sakeni is proceeding with the latest architectural and engineering practices and is expected to be completed by the end of 2026.