Construction Works on the "Chantan" Project

Construction work on the "Chantan" project is actively underway!



In the "Chantan" project, the following works have been completed:

  • Installation of the foundation slab in Block A;

  • Construction of more than 60% of the monolithic walls of the basement level, with reinforcement ongoing on the remaining sections.

Currently in progress:

  • Installation of the slab for floor -1;

  • Waterproofing of the perimeter walls.

At the end of August, the installation of foundation piles is scheduled to begin in the high-rise Block B section.