Construction Works on the "Sakeni" Project

Construction works are actively progressing on the "Sakeni" project!

The following construction works have already been completed:

  • Monolithic structure of the 31st floor

  • Installation of wall and partition blocks on 5 residential floors

At this stage, the following construction works are in progress:

  • Preparatory works for the Schüco glazing system

  • Installation of engineering and fire protection systems in the parking area

  • Installation of Swiss Schindler elevators

  • Installation of the aluminum facade system

  • Installation of the NBK terracotta ventilated facade

In the apartments, the following construction works are in progress:

  • Electrical wiring installation

  • Installation of ventilation ducts

  • Installation of sanitary risers