Construction Works on the "Hisni" Project

Construction works on the "Hisni" project are actively progressing, and the preparatory works have already been completed.

In Blocks I and II of the "Hisni" project

The following construction works have been completed:

  • Installation of foundation piles
  • Excavation and removal of soil from the basement area
  • Cutting pile heads to the design level
  • Leveling the base of the foundation

At this stage, the following construction works are in progress:

  • Preparation of the base layer for the foundation slab
  • Preparatory works for the waterproofing of the foundation slab