Construction Works on the "Hisni" Project
Publish date:
20.11.2025

Construction works on the "Hisni" project are actively progressing, and the preparatory works have already been completed.

In Blocks I and II of the "Hisni" project
The following construction works have been completed:
- Installation of foundation piles
- Excavation and removal of soil from the basement area
- Cutting pile heads to the design level
- Leveling the base of the foundation

At this stage, the following construction works are in progress:
- Preparation of the base layer for the foundation slab
- Preparatory works for the waterproofing of the foundation slab