Construction works are actively progressing on the "Bare" project.

A construction fence has been installed, utilities have been relocated, and temporary infrastructure has been set up.

In the “Bare” project
The following works have already been completed:
Perimeter reinforcement works in the basement area
Soil excavation and removal works
Waterproofing works on the foundation slab
Installation/pouring of the foundation slab

At this stage, reinforcement is in progress for the monolithic walls and columns.