Construction Works on the "Sakeni" Project

Construction work on the "Sakeni" project is actively underway and the following have already been completed:
Construction of the monolithic frame up to the 22nd floor, including 12 residential floors;
Completion of the slab works on the 12th floor of the residential block;
Construction of the monolithic frame and slab for the swimming pool;
Installation of Schüco glazing profiles in the commercial, office, and parking areas;
Masonry works in the commercial, office, and parking zones.

Currently, the following works are in progress:
Installation of vertical structural elements on the 13th floor;
Glazing of Schüco façade systems in the pedestal section.
Construction of the pedestal parapet;
Masonry works on the residential floors.

By the end of August, the following works are scheduled to begin:
Installation of Schindler elevators;
Installation of the NBK terracotta cladding substructure on the façade;
Piping and cabling work for fire safety, water supply, sewage, and electricity systems.