article
Construction Works at Project "Bare"
Publish date:
26.02.2026

Construction works at Project “Bare” are actively progressing, and the following has already been completed:
Installation of the vertical structural elements of the second residential building
Waterproofing works
Currently in progress:
Ramp construction works
Installation of the roof slab for the second residential building
In the near future, it is planned to:
Complete 90% of the monolithic works
Commence blockwork installation works
Across all “Biograpi Living” projects, construction works are carried out with continuous quality monitoring and full adherence to deadlines.



